Share:

I-85 over OSANIPPA CREEK

Map 

Coordinates:
+32.79369, -85.23789
32°47'37" N, 85°14'16" W
Source: National Bridge Inventory (2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:I-85 over OSANIPPA CREEK
Structure number:007258
Location:3 MI N CUSSETA ROAD
Purpose:Carries highway over waterway
Route classification:Principal Arterial - Interstate (Rural) [01]
Length of largest span:73.2 ft. [22.3 m]
Total length:429.2 ft. [130.8 m]
Roadway width between curbs:27.9 ft. [8.5 m]
Deck width edge-to-edge:30.8 ft. [9.4 m]
Skew angle:30°
Owner:State Highway Agency [01]
Year built:1962
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:3
Main spans material:Concrete continuous [2]
Main spans design:Tee beam [04]
Deck type:Concrete Cast-in-Place [1]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:13,725 [as of 2008]
Truck traffic:22% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:53.1 tons [48.3 metric tons]
Inventory rating:31.9 tons [29.0 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:59.9
Recommended work:Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Estimated cost of work:$4,399,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:20,330 [as of 1996]
Truck traffic:20% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:47.9 tons [43.5 metric tons]
Inventory rating:36.0 tons [32.7 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:64.0
Recommended work:Widening of existing bridge or other major structure without deck rehabilitation or replacement [33]
Estimated cost of work:$927,000