Share:

ALMADEN NB-LINCOLN over ALMADEN EXPWY SB

Map 

Coordinates:
+37.28500, -121.88333
37°17'06" N, 121°52'60" W
Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:ALMADEN NB-LINCOLN over ALMADEN EXPWY SB
Structure number:37C0099
Location:AT ALMADEN EXPWY
Purpose:Carries highway and pedestrian walkway over highway
Route classification:Minor Arterial (Urban) [16]
Length of largest span:86.9 ft. [26.5 m]
Total length:355.0 ft. [108.2 m]
Roadway width between curbs:21.0 ft. [6.4 m]
Deck width edge-to-edge:24.9 ft. [7.6 m]
Vertical clearance below bridge:14.8 ft. [4.5 m]
Owner:County Highway Agency [02]
Year built:1961
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:5
Main spans material:Concrete continuous [2]
Main spans design:Box beam or girders - Multiple [05]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:40,840 [as of 2004]
Truck traffic:5% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Good [7 out of 9]
Scour condition:Bridge not over waterway. [N]
Operating rating:74.8 tons [68.0 metric tons]
Inventory rating:44.9 tons [40.8 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:74.1
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$1,380,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:10,000 [as of 1998]
Truck traffic:5% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Good [7 out of 9]
Scour condition:Bridge not over waterway. [N]
Operating rating:74.8 tons [68.0 metric tons]
Inventory rating:44.9 tons [40.8 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:77.8
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$1,480,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:10,000 [as of 1985]
Truck traffic:5% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Very Good [8 out of 9]
Scour condition:Bridge not over waterway. [N]
Operating rating:74.2 tons [67.5 metric tons]
Inventory rating:44.6 tons [40.5 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:89.2