Facts 

Name:CHANNEL LANE over SANTA MONICA CYN DRAIN
Structure number:53C1057
Location:0.1 N/O ENTRADA DR
Purpose:Carries highway over waterway
Route classification:Local (Urban) [19]
Length of largest span:29.9 ft. [9.1 m]
Total length:33.1 ft. [10.1 m]
Roadway width between curbs:19.0 ft. [5.8 m]
Deck width edge-to-edge:24.3 ft. [7.4 m]
Skew angle:
Owner:City or Municipal Highway Agency [04]
Year built:1940
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:M 18 / H 20 [4]
Main span material:Concrete [1]
Main span design:Slab [01]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:120 [as of 2000]
Truck traffic:1% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:79.5 tons [72.3 metric tons]
Inventory rating:47.9 tons [43.5 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:93.0
Recommended work:Other structural work, including hydraulic replacements. [38]

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:120 [as of 1998]
Truck traffic:1% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:43.9 tons [39.9 metric tons]
Inventory rating:27.9 tons [25.4 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:72.0
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$135,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:120 [as of 1989]
Truck traffic:1% of total traffic
Deck condition:Very Good [8 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Channel protection:There are no noticeable or noteworthy deficiencies which affect the condition of the channel. [9]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:52.5 tons [47.7 metric tons]
Inventory rating:33.7 tons [30.6 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:77.4
Recommended work:Bridge rehabilitation because of general structure deterioration or inadequate strength. [35]
Estimated cost of work:$54,000