SB PENA BLVD over SECOND CREEK TRIB

Map 

Coordinates:
+39.83440, -104.73024
39°50'04" N, 104°43'49" W
Source: National Bridge Inventory (2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:SB PENA BLVD over SECOND CREEK TRIB
Structure number:D-31-PB-310
Location:WEST OF TOWER ROAD
Purpose:Carries highway over waterway
Route classification:Principal Arterial - Other Freeways or Expressways (Urban) [12]
Length of largest span:143.1 ft. [43.6 m]
Total length:148.3 ft. [45.2 m]
Roadway width between curbs:40.0 ft. [12.2 m]
Deck width edge-to-edge:42.7 ft. [13.0 m]
Skew angle:
Owner:City or Municipal Highway Agency [04]
Year built:1993
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Main span material:Prestressed concrete [5]
Main span design:Box beam or girders - Multiple [05]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:17,006 [as of 2009]
Truck traffic:6% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:84.3 tons [76.6 metric tons]
Inventory rating:50.5 tons [45.9 metric tons]
Sufficiency rating:96.4

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:22,659 [as of 1998]
Truck traffic:6% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:83.2 tons [75.6 metric tons]
Inventory rating:49.5 tons [45.0 metric tons]
Sufficiency rating:97.9