Share:

NB K15 TO I135 RMP over GYPSUM CREEK

Map 

Coordinates:
+37.63986, -97.30676
37°38'23" N, 97°18'24" W
Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:NB K15 TO I135 RMP over GYPSUM CREEK
Structure number:999913500870111
Location:1.18 MI. N. I-35(KTA)
Purpose:Carries highway over waterway
Route classification:Principal Arterial - Interstate (Urban) [11]
Length of largest span:60.0 ft. [18.3 m]
Total length:151.3 ft. [46.1 m]
Roadway width between curbs:36.1 ft. [11.0 m]
Deck width edge-to-edge:38.1 ft. [11.6 m]
Skew angle:43°
Owner:State Highway Agency [01]
Year built:1966
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:3
Main spans material:Concrete continuous [2]
Main spans design:Slab [01]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Low slump Concrete [4]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:30,600 [as of 2009]
Truck traffic:10% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Operating rating:67.9 tons [61.7 metric tons]
Inventory rating:40.9 tons [37.2 metric tons]
Sufficiency rating:96.1
Recommended work:Bridge deck replacement with only incidental widening. [37]
Estimated cost of work:$188,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:3,720 [as of 1999]
Truck traffic:6% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for assessed or calculated scour condition. [5]
Operating rating:59.4 tons [54.0 metric tons]
Inventory rating:35.6 tons [32.4 metric tons]
Sufficiency rating:96.6
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$781,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:3,720 [as of 1990]
Truck traffic:8% of total traffic
Deck condition:Very Good [8 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Scour calculation/evaluation has not been made. [6]
Operating rating:51.5 tons [46.8 metric tons]
Inventory rating:31.0 tons [28.2 metric tons]
Sufficiency rating:95.1