Share:

I-435 HWY SB over URB2524, PARALLEL RD

Map 

Coordinates:
+39.12856, -94.81673
39°07'43" N, 94°49'00" W
Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:I-435 HWY SB over URB2524, PARALLEL RD
Structure number:999943501052211
Location:0.89 MI.NORTH OF US-24,SB
Purpose:Carries highway over highway
Route classification:Principal Arterial - Interstate (Urban) [11]
Length of largest span:70.9 ft. [21.6 m]
Total length:234.3 ft. [71.4 m]
Roadway width between curbs:64.0 ft. [19.5 m]
Deck width edge-to-edge:65.9 ft. [20.1 m]
Vertical clearance below bridge:16.1 ft. [4.9 m]
Skew angle:20°
Owner:State Highway Agency [01]
Year built:1983
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18+Mod / HS 20+Mod [6]
Number of main spans:4
Main spans material:Steel continuous [4]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Low slump Concrete [4]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:17,150 [as of 2009]
Truck traffic:8% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Very Good [8 out of 9]
Scour condition:Bridge not over waterway. [N]
Operating rating:58.9 tons [53.5 metric tons]
Inventory rating:30.9 tons [28.1 metric tons]
Sufficiency rating:89.4
Recommended work:Bridge deck replacement with only incidental widening. [37]
Estimated cost of work:$517,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:11,705 [as of 1999]
Truck traffic:6% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Scour condition:Bridge not over waterway. [N]
Operating rating:58.4 tons [53.1 metric tons]
Inventory rating:30.7 tons [27.9 metric tons]
Sufficiency rating:89.7
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$1,210,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:8,200 [as of 1990]
Truck traffic:9% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Scour condition:Bridge not over waterway. [N]
Operating rating:38.1 tons [34.6 metric tons]
Inventory rating:28.5 tons [25.9 metric tons]
Sufficiency rating:96.4