Share:

OFF-RAMP I-83 NB over JONES FALLS

Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:OFF-RAMP I-83 NB over JONES FALLS
Structure number:200000BC3122010
Location:NB I-83 TO WB N PKWY
Purpose:Carries highway over waterway
Route classification:Principal Arterial - Interstate (Urban) [11]
Length of largest span:65.9 ft. [20.1 m]
Total length:150.9 ft. [46.0 m]
Roadway width between curbs:24.9 ft. [7.6 m]
Deck width edge-to-edge:28.2 ft. [8.6 m]
Skew angle:13°
Owner:City or Municipal Highway Agency [04]
Year built:1959
Year reconstructed:1987
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:3
Main spans material:Steel [3]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:23,800 [as of 2007]
Truck traffic:5% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Operating rating:79.2 tons [72.0 metric tons]
Inventory rating:40.6 tons [36.9 metric tons]
Sufficiency rating:96.7
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$36,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:20,499 [as of 1994]
Truck traffic:5% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Operating rating:79.2 tons [72.0 metric tons]
Inventory rating:40.6 tons [36.9 metric tons]
Sufficiency rating:97.1
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$23,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:20,499 [as of 1988]
Deck condition:Very Good [8 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge not over waterway. [N]
Operating rating:55.4 tons [50.4 metric tons]
Inventory rating:31.7 tons [28.8 metric tons]
Sufficiency rating:94.6