BROENING HIGHWAY over COLGATE CREEK

Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:BROENING HIGHWAY over COLGATE CREEK
Structure number:200000BC4202010
Location:1.5 MI W I-895
Purpose:Carries highway and pedestrian walkway over waterway
Route classification:Local (Urban) [19]
Length of largest span:78.1 ft. [23.8 m]
Total length:578.1 ft. [176.2 m]
Roadway width between curbs:58.1 ft. [17.7 m]
Deck width edge-to-edge:70.2 ft. [21.4 m]
Skew angle:15°
Owner:City or Municipal Highway Agency [04]
Year built:1968
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:10
Main spans material:Prestressed concrete [5]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:23,000 [as of 2007]
Truck traffic:5% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Fair [5 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Pier/abutment protection:Navigation protection not required [1]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Operating rating:48.5 tons [44.1 metric tons]
Inventory rating:28.7 tons [26.1 metric tons]
Sufficiency rating:76.8
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$241,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:20,557 [as of 1994]
Truck traffic:5% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Fair [5 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Pier/abutment protection:Navigation protection not required [1]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Operating rating:48.5 tons [44.1 metric tons]
Inventory rating:41.6 tons [37.8 metric tons]
Sufficiency rating:83.6
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$227,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:8,379 [as of 1988]
Deck condition:Good [7 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge not over waterway. [N]
Operating rating:48.5 tons [44.1 metric tons]
Inventory rating:31.7 tons [28.8 metric tons]
Sufficiency rating:94.5