Share:

CENTRAL AVENUE over HARFORD RUN

Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:CENTRAL AVENUE over HARFORD RUN
Structure number:200000BC8019010
Location:ALICEANNA AT CENTRAL AVE
Purpose:Carries highway and pedestrian walkway over waterway
Route classification:Local (Urban) [19]
Length of largest span:24.0 ft. [7.3 m]
Total length:24.9 ft. [7.6 m]
Roadway width between curbs:69.6 ft. [21.2 m]
Deck width edge-to-edge:69.6 ft. [21.2 m]
Owner:City or Municipal Highway Agency [04]
Year built:1920
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Main span material:Steel [3]
Main span design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:28,785 [as of 2007]
Truck traffic:5% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Inventory rating:59.4 tons [54.0 metric tons]
Sufficiency rating:96.3
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$26,000

2000 Inspection 

Status:Open, no restriction [A]
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Scour calculation/evaluation has not been made. [6]
Inventory rating:59.4 tons [54.0 metric tons]
Sufficiency rating:100.0
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$93,000

1992 Inspection 

Status:Open, no restriction [A]
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge not over waterway. [N]
Inventory rating:59.4 tons [54.0 metric tons]
Evaluation:Functionally obsolete [2]
Sufficiency rating:96.0