Facts 

Name:TOWNSHIP ROAD over E BR VERDIGRIS CREEK
Structure number:C000221945
Location:5N OF ROYAL
Purpose:Carries highway over waterway
Route classification:Local (Rural) [09]
Length of largest span:49.9 ft. [15.2 m]
Total length:50.9 ft. [15.5 m]
Roadway width between curbs:15.7 ft. [4.8 m]
Deck width edge-to-edge:15.7 ft. [4.8 m]
Owner:County Highway Agency [02]
Year built:1935
Year reconstructed:1975
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Main span material:Steel [3]
Main span design:Truss - Thru [10]
Deck type:Wood or Timber [8]
Wearing surface:Wood or Timber [7]

2010 Inspection 

Status:Posted for load [P]
Average daily traffic:10 [as of 2003]
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Pier/abutment protection:Navigation protection not required [1]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Operating rating:19.8 tons [18.0 metric tons]
Inventory rating:11.9 tons [10.8 metric tons]
Sufficiency rating:43.6
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$168,000

2000 Inspection 

Status:Posted for load [P]
Average daily traffic:10 [as of 1997]
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge is scour critical; bridge foundations determined to be unstable. [3]
Operating rating:25.7 tons [23.4 metric tons]
Inventory rating:11.9 tons [10.8 metric tons]
Sufficiency rating:43.6

1992 Inspection 

Status:Posted for load [P]
Average daily traffic:10 [as of 1990]
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Scour calculation/evaluation has not been made. [6]
Operating rating:26.0 tons [23.6 metric tons]
Inventory rating:12.4 tons [11.3 metric tons]
Sufficiency rating:50.8
Recommended work:Replacement of bridge or other structure because of substandard load carrying capacity or substantial bridge roadway geometry. [31]
Estimated cost of work:$110,000