Facts 

Name:EB-I80 over BIG PAPIL CR/82ND ST&AVE
Structure number:S080 44846R
Location:OMAHA I80 @ 82ND ST
Purpose:Carries highway over highway and waterway
Route classification:Principal Arterial - Interstate (Urban) [11]
Length of largest span:109.9 ft. [33.5 m]
Total length:303.2 ft. [92.4 m]
Roadway width between curbs:107.0 ft. [32.6 m]
Deck width edge-to-edge:109.3 ft. [33.3 m]
Vertical clearance below bridge:14.1 ft. [4.3 m]
Skew angle:18°
Owner:State Highway Agency [01]
Year built:1961
Year reconstructed:1987
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 22.5 / HS 25 [9]
Number of main spans:3
Main spans material:Steel continuous [4]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:80,955 [as of 2008]
Truck traffic:6% of total traffic
Deck condition:Very Good [8 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Pier/abutment protection:Navigation protection not required [1]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:60.4 tons [54.9 metric tons]
Inventory rating:35.6 tons [32.4 metric tons]
Sufficiency rating:89.3

2000 Inspection 

Average daily traffic:500 [as of 1997]
Truck traffic:10% of total traffic
Evaluation:Not applicable [N]

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:49,770 [as of 1990]
Truck traffic:8% of total traffic
Deck condition:Very Good [8 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:35.6 tons [32.4 metric tons]
Inventory rating:35.6 tons [32.4 metric tons]
Sufficiency rating:93.2