Facts 

Name:WHISKEY BRIDGE over GENESEE RIVER
Structure number:000000003319860
Location:0.9 MI S PORTAGEVILLE
Purpose:Carries highway over waterway
Route classification:Local (Rural) [09]
Length of largest span:99.7 ft. [30.4 m]
Total length:402.9 ft. [122.8 m]
Roadway width between curbs:30.5 ft. [9.3 m]
Deck width edge-to-edge:33.8 ft. [10.3 m]
Owner:County Highway Agency [02]
Year built:1973
Year reconstructed:2001
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:4
Main spans material:Steel [3]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]

Latest Available Inspection: June 2011 

Status:Open, no restriction [A]
Average daily traffic:94 [as of 2002]
Truck traffic:2% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Fair [5 out of 9]
Structural appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Deck geometry appraisal:Better than present minimum criteria [7]
Water adequacy appraisal:Somewhat better than minimum adequacy to tolerate being left in place as is [5]
Roadway alignment appraisal:Equal to present desirable criteria [8]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:57.9 tons [52.6 metric tons]
Inventory rating:35.0 tons [31.8 metric tons]
Sufficiency rating:87.8
Recommended work:Widening of existing bridge with deck rehabilitation or replacement. [34]
Estimated cost of work:$5,331,000

Previous Inspections 

DateSuff. ratingEvaluationDeckSuper.Sub.ADT
June 201187.8Not deficientGoodGoodFair94
May 200988.0Not deficientGoodGoodFair94
September 200788.0Not deficientGoodGoodFair94
October 200588.0Not deficientVery GoodGoodFair94
September 200389.0Not deficientExcellentGoodFair94
November 200197.1Not deficientExcellentGoodSatisfactory242
June 200085.0Not deficientFairFairFair242
August 199885.0Not deficientFairFairFair242
July 199666.9Structurally deficientPoorPoorPoor25
July 199469.9Structurally deficientSatisfactoryPoorPoor25
August 199284.9Not deficientSatisfactoryFairFair25
September 199082.9Not deficientFairFairFair25