Share:

IR90-WB over CEI OUTLET CHANNEL

Map 

Coordinates:
+41.53722, -81.64111
41°32'14" N, 81°38'28" W
Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:IR90-WB over CEI OUTLET CHANNEL
Structure number:1808311
Location:.23 MI W OF JCT SR283DA
Purpose:Carries highway over waterway
Route classification:Principal Arterial - Interstate (Urban) [11]
Length of largest span:60.0 ft. [18.3 m]
Total length:184.1 ft. [56.1 m]
Roadway width between curbs:73.8 ft. [22.5 m]
Deck width edge-to-edge:78.4 ft. [23.9 m]
Owner:State Highway Agency [01]
Year built:1952
Year reconstructed:2005
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:3
Main spans material:Steel continuous [4]
Main spans design:Stringer/Multi-beam or girder [02]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Integral Concrete (separate non-modified layer of concrete added to structural deck) [2]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:62,815 [as of 2007]
Truck traffic:6% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:44.6 tons [40.5 metric tons]
Inventory rating:35.6 tons [32.4 metric tons]
Sufficiency rating:89.2

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:59,255 [as of 1991]
Truck traffic:8% of total traffic
Deck condition:Poor [4 out of 9]
Superstructure condition:Satisfactory [6 out of 9]
Substructure condition:Satisfactory [6 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:44.6 tons [40.5 metric tons]
Inventory rating:35.6 tons [32.4 metric tons]
Evaluation:Structurally deficient [1]
Sufficiency rating:86.4

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:118,620 [as of 1988]
Truck traffic:8% of total traffic
Deck condition:Satisfactory [6 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:59.4 tons [54.0 metric tons]
Inventory rating:39.6 tons [36.0 metric tons]
Sufficiency rating:85.0