Share:

SE 92ND AVE over B-68 OVER JOHNSON CREEK

Map 

Coordinates:
+45.46819, -122.56855
45°28'05" N, 122°34'07" W
Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:SE 92ND AVE over B-68 OVER JOHNSON CREEK
Structure number:11070A000 00001
Location:S OF SE FLAVEL ST
Purpose:Carries highway and pedestrian walkway over waterway
Route classification:Collector (Urban) [17]
Length of largest span:65.0 ft. [19.8 m]
Total length:128.0 ft. [39.0 m]
Roadway width between curbs:60.0 ft. [18.3 m]
Deck width edge-to-edge:78.1 ft. [23.8 m]
Skew angle:14°
Owner:City or Municipal Highway Agency [04]
Year built:1975
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:MS 18 / HS 20 [5]
Number of main spans:3
Main spans material:Concrete continuous [2]
Main spans design:Slab [01]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Monolithic Concrete (concurrently placed with structural deck) [1]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:9,105 [as of 2007]
Truck traffic:5% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Good [7 out of 9]
Substructure condition:Good [7 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:49.9 tons [45.4 metric tons]
Inventory rating:29.9 tons [27.2 metric tons]
Sufficiency rating:92.1

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:8,250 [as of 1996]
Truck traffic:5% of total traffic
Deck condition:Good [7 out of 9]
Superstructure condition:Very Good [8 out of 9]
Substructure condition:Very Good [8 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:49.5 tons [45.0 metric tons]
Inventory rating:29.7 tons [27.0 metric tons]
Sufficiency rating:94.9
Recommended work:Replacement of bridge or other structure because of relocation of road. [32]
Estimated cost of work:$1,607,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:12,100 [as of 1989]
Truck traffic:10% of total traffic
Deck condition:Very Good [8 out of 9]
Superstructure condition:Excellent [9 out of 9]
Substructure condition:Excellent [9 out of 9]
Channel protection:Bank protection is in need of minor repairs. River control devices and embankment protection have a little minor damage. Banks and/or channel have minor amounts of drift. [7]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:49.5 tons [45.0 metric tons]
Inventory rating:35.6 tons [32.4 metric tons]
Sufficiency rating:100.0