HENRY AVENUE over SEPTA;CSX AND CREEK

Map 

Coordinates:
+40.00733, -75.17965
40°00'26" N, 75°10'47" W
Source: National Bridge Inventory (1992, 2000, 2010 editions)
Information not verified. Use at your own risk.

Facts 

Name:HENRY AVENUE over SEPTA;CSX AND CREEK
Structure number:674001002005880
Location:N.HUNTING PARK AVE.28D02
Purpose:Carries highway and pedestrian walkway over railroad and waterway
Route classification:Other Principal Arterial (Urban) [14]
Length of largest span:92.9 ft. [28.3 m]
Total length:562.0 ft. [171.3 m]
Roadway width between curbs:76.1 ft. [23.2 m]
Deck width edge-to-edge:96.5 ft. [29.4 m]
Vertical clearance below bridge:19.7 ft. [6.0 m]
Skew angle:99°
Owner:State Highway Agency [01]
Year built:1930
Historic significance:Bridge is not eligible for the National Register of Historic Places [5]
Design load:M 13.5 / H 15 [2]
Number of main spans:5
Main spans material:Concrete continuous [2]
Main spans design:Girder and floorbeam system [03]
Deck type:Concrete Cast-in-Place [1]
Wearing surface:Bituminous [6]

2010 Inspection 

Status:Open, no restriction [A]
Average daily traffic:6,561 [as of 2010]
Truck traffic:7% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Fair [5 out of 9]
Substructure condition:Serious [3 out of 9]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Bridge foundations determined to be stable for the assessed or calculated scour condition. [8]
Operating rating:80.9 tons [73.5 metric tons]
Inventory rating:49.0 tons [44.5 metric tons]
Evaluation:Structurally deficient [1]
Sufficiency rating:48.8
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$4,000

2000 Inspection 

Status:Open, no restriction [A]
Average daily traffic:16,069 [as of 2000]
Truck traffic:7% of total traffic
Deck condition:Fair [5 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Serious [3 out of 9]
Channel protection:Bank is beginning to slump. River control devices and embankment protection have widespread minor damage. There is minor stream bed movement evident. Debris is restricting the channel slightly. [6]
Scour condition:Scour calculation/evaluation has not been made. [6]
Operating rating:47.5 tons [43.2 metric tons]
Inventory rating:28.7 tons [26.1 metric tons]
Evaluation:Structurally deficient [1]
Sufficiency rating:44.3
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$4,222,000

1992 Inspection 

Status:Open, no restriction [A]
Average daily traffic:22,086 [as of 1992]
Deck condition:Fair [5 out of 9]
Superstructure condition:Poor [4 out of 9]
Substructure condition:Poor [4 out of 9]
Channel protection:Banks are protected or well vegetated. River control devices such as spur dikes and embankment protection are not required or are in a stable condition. [8]
Scour condition:Bridge foundations determined to be stable for assessed or calculated scour conditions; field review indicates action is required. [4]
Operating rating:89.1 tons [81.0 metric tons]
Inventory rating:53.5 tons [48.6 metric tons]
Evaluation:Structurally deficient [1]
Sufficiency rating:59.7
Recommended work:Other structural work, including hydraulic replacements. [38]
Estimated cost of work:$7,334,000